Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Kabupaten |
: |
Kota Jakarta Selatan |
Kode Pos |
: |
12950 |
Telepon |
: |
021-5221246 |
Fax |
: |
021-5200675 |
|
|
: |
[email protected] |
Website |
: |
www.krakataueng.co.id |
NPWP |
: |
01.067.815.9-051.000 |
Bentuk Badan Usaha |
: |
PT |
Jenis Badan Usaha |
: |
Konsultan Lainnya |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
| No | Sub Bidang Klasifikasi/Layanan | Nomor Kode | Kualifikasi | Kemampuan Dasar | Asosiasi | Tgl Permohonan | Tgl Cetak Pertama | Tgl Cetak Perubahan Terakhir | Tgl Reg Th2 | |
|---|---|---|---|---|---|---|---|---|---|---|
| Tahun | Nilai (Rp. Juta) |
|||||||||
| 1 | Jasa Pelaksana Konstruksi Instalasi Pembangkit Tenaga Listrik Semua Daya | EL001 | B2 | 2014 | 1924703 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 2 | Jasa Pelaksana Instalasi Pembangkit Tenaga Listrik daya maksimum 10 MW | EL002 | B1 | 2012 | 210762 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 3 | Jasa Pelaksana Instalasi Jaringan Transmisi Tenaga Listrik Tegangan Tinggi/Ekstra Tegangan Tinggi | EL004 | B2 | 2012 | 306036 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 4 | Jasa Pelaksana Konstruksi Jaringan Distribusi Tenaga Listrik Tegangan Menengah | EL006 | B1 | 2012 | 308938 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 5 | Jasa Pelaksana Instalasi Jaringan Distribusi Tenaga Listrik Tegangan Rendah | EL007 | B1 | 2011 | 193771 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 6 | Jasa Pelaksana instalasi Sistem Kontrol dan Instrumentasi | EL009 | B2 | 2012 | 355101 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 7 | Jasa Pelaksana Instalasi Tenaga Listrik Gedung dan Pabrik | EL010 | B1 | 2010 | 216554 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
| 8 | Jasa Pelaksana Konstruksi Instalasi Elektrikal Lainnya | EL011 | B2 | 2008 | 305540 | AKLI | 2018-02-21 | 2018-03-29 | 2018-05-09 | |
Subklasifikasi yang tidak terbit karena belum registrasi tahun ke-2 atau ke-3 |
Catatan Proses (*) |
0. Permohonan Registrasi |
1. Proses Penilaian di Unit Sertifikasi |
2. Selesai Penilain di Unit Sertifikasi |
3. Proses Periode Registrasi |
4. Cetak Sertifikat |
5. Proses Pembayaran |
6. Selesai |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
|
|
||
|---|---|---|
| No Akte |
|
16 |
| Nama Notaris |
|
Ny. R. Arie Sutardjo, SH. |
| Alamat |
|
Jl. Kelapa Hijau VII Blok Q IV/II Kompl. Billy & Moon , Pondok Kelapa, Jakarta Timur Tlp. 8197302 |
| Kota / Kabupaten |
|
Kota Jakarta Timur |
| Propinsi |
|
DKI Jakarta |
| Tanggal Akte |
|
12-October-1988 |
|
|
|||||
|---|---|---|---|---|---|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||
|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
13 | Tuti Setiahati K. Soetoro, SH. | Jl. Bangka No. 106 B Pela Mampang - Jakarta Selatan , Tlp. 7995390 | Kota Jakarta Selatan | DKI Jakarta |
|
|
2 | Tuti Setiahati K. Soetoro, SH. | Jl. RS. Fatmawati No. 39, Blok C2-08, Jakarta Selatan Tlp. 7210726 | Kota Jakarta Selatan | DKI Jakarta |
|
|
80 | Imas Fatimah, SH. | Graha MIK Lt. 5 Taman Perkantoran Kuningan Jl. Setiabudi Selatan Kav. 16-17, Tlp. 57941450 | Kota Jakarta Selatan | DKI Jakarta |
|
|
39 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
20 | Ny. Hj. Erna Yudhaningsih, SH | Jl. SA. Tirtayasa No. 144 C, Cilegon, Banten Tlp. 0254-377116 | Kota Cilegon | Banten |
|
|
27 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
29 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
92 | Ny. Hj. Erna Yudhaningsih, SH. | Komplek Ruko Mega Cilegon, Blok A No. 10 - Simpang Tiga, Cilegon, Banten, Tlp. 0254-377116 | Kota Cilegon | Banten |
|
|
18 | Ny. Hj. Erna Yudhaningsih, SH. | Komplek Ruko Mega Cilegon, Blok A No. 10, Simpang Tiga, Cilegon, Banten, Tlp. 0254-377116 | Kota Cilegon | Banten |
|
|
05 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
19 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
10 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
26 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
05- | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
55 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
25 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
|
|
40 | Ny Indrajati Tandjung, SH. | Jl. Jend. Ahmad Yani (Raya Cilegon) No. 11, Cilegon, Banten 42421 Telp 0254 394092 | Kota Cilegon | Banten |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
|
|
|
|
|
|
|
|
|---|---|---|---|---|---|---|
|
|
Drs. Ganda Kusuma | 09-June-1961 | Perumahan Kalibata indah Blok P No. 5, RT 04 RW 06, Kel. Rawajati, Kec Pancoran, Jaksel | 3174080909610003 | Komisaris | S2 |
|
|
Koesma Soemantri | 18-July-1964 | Jl. Kotasari No. 15 RT. 001/03, Kel-Kotabumi, Kec- Purwakarta | 3672071807640001 | Direktur | S1 |
|
|
Hery Susanto | 12-June-1966 | BBS III Blok E-1 No. 01, RT. 017/09, Kel-Ciwaduk, Kec-Cilegon | 3672021206660002 | Komisaris | S1 |
|
|
Lussy Adriaty Dede | 08-April-1968 | Perum Orchid Bintaro Kav. 68 | 3674034804680002 | Direktur Utama | S2 |
|
|
Odi Rivaldi | 07-September-1967 | Green Beringin Residence, Emerald No. 12A RT/RW 001/026 Kel. Serang Kec. Serang | 367201070967004 | Direktur | S1 |
|
|
Prio Priyono | 20-October-1964 | Komplek Pondok Cilegon Indah Blok E39 No. 11 RT/RW 001/007 Kel. Cibeber, Kec. Cibeber | 3672012010640004 | Direktur | S1 |
|
|
Nandang Hariana, SE. AK. | 01-March-1967 | Komplek PErumahan BCK Blok E06 No.16 RT 04/09, Cibeber Kota Cilegon | 367.2010.10367.0004 | Komisaris Utama | S2 |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
|
|
|||
|---|---|---|---|
| Tahun | 2012 | Pembayaran Wajib Pajak | 52419810 |
| Tahun | 2011 | Pembayaran Wajib Pajak | 33728888 |
|
Omset 5 tahun Terakhir
|
|||||
| Tahun | 2011 | Nilai Omset pada Tahun Bersangkutan (Rp) | 1330181506 | ||
| Tahun | 2011 | Nilai Omset pada Tahun Bersangkutan (Rp) | 2011 | ||
| Tahun | 2010 | Nilai Omset pada Tahun Bersangkutan (Rp) | 997527834 | ||
| Tahun | 2009 | Nilai Omset pada Tahun Bersangkutan (Rp) | 707098568 | ||
| Tahun | 2008 | Nilai Omset pada Tahun Bersangkutan (Rp) | 657713484 | ||
|
Pemilik Saham
|
|
|
|
|
|
|
|
|
|---|---|---|---|---|---|---|---|
|
|
PT. Krakatau Steel (Persero), Tbk | - | Cilegon | 332332054 |
1 |
0.00 |
0.00 |
|
|
PT. Krakatau Industrial Estate Cilegon | - | Jakarta | 1000 |
1 |
0.00 |
0.00 |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
|
|
|
|
|
|
|
|
|
|
|---|---|---|---|---|---|---|---|---|
|
|
HENDRI SYAF | 24 May 1963 | BBS BLOK E-3 NO.03 RT/RW.024/009 KEL.CIWADUK KEC.CILEGON | 3672022406630004 | S1 | 1021785 | AHLI | |
|
|
MUFTI FUADY, S.T | 13 February 1971 | KOMP BPP E2/10 RT/RW : 015/003 KEL. PELAMUNAN KEC. KRAMATWATU KAB. SERANG | 3604051302710002 | S1 | 1029920 | AHLI | |
|
|
IR. FIRJADI PUTRA | 30 September 1964 | PCI BLOK D.84 NO.12 RT/RW.007/005 KEL.CIBEBER KEC.CIBEBER | 3872013009640001 | 1030681 | AHLI | ||
|
|
WENDRI NAZIF | 01 July 1962 | PCI BLOK D 118 NO.9-10 RT.006/004, CIBEBER, CIBEBER | 3672010107620012 | S1 | 1117185 | AHLI | |
|
|
IR. PARLINDUNGAN LUBIS | 13 March 1964 | KOMP. GSI BLOK M1 NO. 7 RT/RW. 003/004 KEL. SERDANG KEC. KRAMATWATU KAB. SERANG | 3604051303640002 | S1 | 1117186 | AHLI | |
|
|
IR. HERU SUNARYONO | 10 March 1963 | PONDOK CILEGON INDAH BLOK D-87 KEL.CIBEBER KEC.CILEGON | 3672011103630003 | S1 | 1117187 | AHLI | |
|
|
YUSRIZAL, S.T | 05 July 1981 | PERUM BBS III BLOK E-3/4 RT/RW. 024/009 KEL.CIWADUK KEC.CILEGON KOTA CILEGON | 3672070507810002 | S1 | 1140978 | AHLI | |
|
|
ARIF GINANJAR, S.T | 30 June 1983 | KOMP BUMI RAKATA ASRI CLUSTER 7 BLOK G-3 NO.4 RT.007/007, CIWEDUS, CILEGON | 3672053006830001 | S1 | 1144398 | AHLI | |
|
|
IMAN RACHMADI | 07 January 1962 | MADANI NO.38 RT.002/002, KOTABUMI, PURWAKARTA | 3672070701620002 | S2 | 1152752 | AHLI |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
|
No
|
Proyek
|
Pemberi Tugas
|
Sub Bidang Kualifikasi
|
Nomor
|
Tanggal
|
|||||||
|
Tahun
|
Nama
|
Nilai Rupiah
(dalam ribuan) |
Kontrak
|
NKPK
|
Berita Acara Serah Terima
|
Berita Acara Serah Terima
|
Kontrak
|
Mulai
|
Selesai
|
|||
|
|
2009 | Pekerjaan Pembangunan 315.000 TPY Reduction Rotary Kiln Plant Kalimantan Ironmaking Project , ada unsur Instalasi Tenaga Listrik Gedung dan Pabrik | 62883678 | PT. Meratus Jaya Iron & Steel | EL010 | 1 | PROJ053/20/MJIS/II/2009 | Provisional Acceptance Certificate tgl 27/5/2010 | 27 May 2010 | 19 February 2009 | 19 February 2009 | 27 May 2010 |
|
|
2008 | Pekerjaan Proyek Peningkatan Fleksibilitas Operasi Naphta Processing Unit | 7535430 | PT. Pertamina (Persero) UP VI Balongan | EL011 | 3 | 002/E10000/2008-S2 | 007/E20300/2012-S4 | 21 March 2012 | 27 November 2008 | 27 November 2008 | 21 March 2012 |
|
|
2010 | EPC Proyek Peningkatan Fleksibilitas Operasi Naphta Processing Unit PT Pertamina UP VI Balongan | 107762762 | PT. Pertamina (Persero) | TI504 | 3 | 002/E10000/2008-S2 | BA Date 31 July 2010 | 31 July 2010 | 27 November 2008 | 27 November 2008 | 31 July 2010 |
|
|
2009 | Pembangunan rumah Susun Sederhana Sewa(Rusunawa) Di Kampung Nglarangan | 6443220 | PT.SURYA ADITAMA | BG002 | 1 | 01.244/SPK-SA/KE-VIII/2009 | 01.247/BA.I-SA/KE-III/2010 | 11 March 2010 | 11 August 2009 | 11 August 2009 | 11 March 2010 |
|
|
2008 | Pembangunan Terminat Transit Bau Bau Sulawesi | 81020945 | PT. Pertamina (Pertamina) | EL011 | 1 | 017/F30000/2008-S5 | BA Operational Acceptance tgl 22/12/2008 | 22 December 2008 | 22 December 2008 | 22 December 2008 | 22 December 2008 |
|
|
2011 | Pekerjaan EPC Owner Scope Combined Cycle Power Plant (Capacity 120 MW) | 60960000 | PT. Krakatau Daya Listrik | EL001 | 1 | 056/DU-KDL/KONTR/0611 | Berita Acara tanggal 16/11/2011 | 16 November 2011 | 01 June 2011 | 01 June 2011 | 16 November 2011 |
|
|
2008 | Pekerjaan Lanjutan Pembangunan Gedung Rumah Sakit Krakatau Medika | 88754932 | PT. Krakatau Medika | BG008 | 1 | 102/KONTR/DU-KM/VII/2008 | 012/BAST.04.RSKM-KE/DIR/2009 | 21 April 2009 | 22 July 2008 | 22 July 2008 | 21 April 2009 |
|
|
2009 | Peningkatan Jalan Kereta Api rel P.38/r.42 Mengganti Bantalan Kayu dengan Beton Malang -Blitar | 84875800 | DIRJEN PERHUBUNGAN DARAT | SI003 | 1 | 20-PP-JT/SPP/III/2009 | 22-PP-JT/BASTP.01/X/2009 | 12 October 2009 | 16 March 2009 | 16 March 2009 | 12 October 2009 |
|
|
2008 | Pembangunan Coal Handling Facilities PT. Cigading International Bulk Terminal, ada unsur Distribusi Tenaga Listrik Tegangan Rendah | 57715289 | PT. Cigading International Bulk Terminal | EL007 | 1 | 20/KONTR/DU-KE/1036/IX/2008 | Taking Over Certificate Tertanggal 3/10/2011 | 03 October 2011 | 01 September 2008 | 01 September 2008 | 03 October 2011 |
|
|
2008 | Pembangunan Coal Handling Facilities PT. Cigading International Bulk Terminal, ada unsur Instalasi Elektrikal Lainnya | 16490082 | PT. Cigading Intel. Bulk Terminal | EL011 | 1 | 20/KONTR/DU-KE/1036/IX/2008 | Taking Over Certificate tgl. 3/10/ 2011 | 03 October 2011 | 01 September 2008 | 01 September 2008 | 03 October 2011 |
|
|
2011 | Design, Construction and Commisioning of Coal Handling Facilities at Cigading International Bulk Terminal-Stage 1 | 328460884 | PT. Cigading International Bulk Terminal | TI501 | 1 | 20/KONTR/DU-KE/1036/IX/2008 | BA Date 3 Oct. 2011 | 29 March 2011 | 01 September 2008 | 01 September 2008 | 29 March 2011 |
|
|
2009 | Pembangunan Slab Steel Plant (SSP-2) Oxy Fuel Burner for Electric Arc Furnaces #9 & #10 Package Revitalization Project of PT. Krakatau Steel | 407745 | PT. Krakatau Steel (Persero) | EL011 | 1 | 21/C/DU-KS/KONTR/2009 | Certificate of Effective Data Tertanggal 15/1/2010 | 15 January 2010 | 20 November 2009 | 20 November 2009 | 15 January 2010 |
|
|
2010 | Pembangunan Direct.Reduction Plant Revitalization Project Hly Zero Reformer PT. Krakatau Steel | 62263477 | PT. Krakatau Steel (Persero) | EL011 | 1 | 36/C/DU-KS/KONTR/2010 | Certificate Tertanggal 15/3/2012 | 15 February 2012 | 27 August 2010 | 27 August 2010 | 15 March 2012 |
|
|
2011 | Pelaksanakan Pekerjaan Penggalian dan Penambangan | 85150985 | PT ENERGY MEGA PERSADA | MK006 | 1 | 441/PERJ-EMP/KE-VIII/2011 | BASTP.01-444/EMP-KE/II/2012 | 13 February 2012 | 11 August 2011 | 11 August 2011 | 13 February 2012 |
|
|
2010 | Pekerjaan Perbaikan Coating Pipa Gas Di Junction 10,Kali Celingsi,Kali Nagrak,K102,TO 6,MLV 8,MLV 6,F5 MLV 11 & Pekerjaan Wrapping Tape Pipa 24 Inchi | 90924322 | PT. INDOKARYA MUSTIKA SEJAHTERA | MK009 | 1 | 574.11/PERJ-IMS/B.255/DIR-VII/2010-KE | 584.11/BAST.01-IMS/B.255/DIR-I/2011-KE | 31 January 2011 | 22 July 2010 | 22 July 2010 | 31 January 2011 |
|
|
2007 | Benfiled Solution Pipe Columb AND Gases and Oil Maintance System | 86850600 | PT. TUGU PRADANA INDONESIA | SI007 | 1 | A No.110/TPI/07.2007 | A No.115/HOWFS.1-TPI/09/2007 | 24 September 2007 | 16 July 2007 | 16 July 2007 | 24 September 2007 |
|
|
2010 | Pekerjaan Pembangunan Asam -Asam CPP and OLC Project , ada unsur Instalasi Sistem Kontrol dan Instrumentasi | 108420156 | PT. Nusa Tambang Pratama | EL009 | 1 | ASM/10/C05A -ASM/10/C05B | Certificate Completion tertanggal 27/12/2012 | 27 December 2012 | 22 November 2010 | 22 November 2010 | 27 December 2012 |
|
|
2010 | Pekerjaan Pembangunan Asam -Asam CPP and OLC Project, ada unsur Instalasi Elektrikal Lainnya | 39827812 | PT. Nusa Tambang Pratama | EL011 | 1 | ASM/10/C05A-ASM/10/C05B | Certificate Of Practical Completion tgl 27/12/2012 | 27 December 2012 | 22 November 2010 | 22 November 2010 | 27 December 2012 |
|
|
2010 | Pekerjaan Pembangunan Conveyor Land, Asam-Asam CPP | 93439500 | PT. Nusa Tambang Pratama | EL004 | 1 | ASM/10/CO5A-B | Certificate of Practical Completion 27/12/2012 | 27 December 2012 | 22 November 2010 | 22 November 2010 | 27 December 2012 |
|
|
2010 | Pekerjaan Penggantian Pipa Header Pompa Pruoduk Dari DIA 6 "Menjadi 12" Pengganti 3 Unit Pompa Produk KAP.500 GPM Pada Pabrik Bioethanol Malang | 84806370 | PT. SARAN ENERGI TEKNINDO | MK007 | 1 | B.068/KONT-SET/142/DIR-III/2010-KE | B.075/BAST.01-SET/142/DIR-XI/2010-KE | 29 November 2010 | 26 March 2010 | 26 March 2010 | 29 November 2010 |
|
|
2009 | Proyek Pemasangan Pipa Baja (steel) Distribusi Primer Karang Pilang III | 29159944 | PDAM Kota Surabaya | SI008 | 3 | BA.A/18/436.8.1/2009 | ST/01/JAR/KP.III/XII/2010 | 29 December 2010 | 16 April 2009 | 16 April 2009 | 29 December 2010 |
|
|
2010 | Pembangunan Hotel Permata Krakatau di Cilegon | 87459000 | PT. Krakatau Industrial Estate Cilegon | BG006 | 1 | HK.02.01/0034/2010 | BAST.22.02/PEMB.HPK/KIEC/2012 | 22 February 2012 | 20 December 2010 | 20 December 2010 | 22 February 2012 |
|
|
2010 | Pembangunan Hotel Lantai 5 PT. KIEC | 27270000 | PT. Krakatau Industrial Estate Cilegon | EL010 | 1 | HK.02.01/0034/2010 | Certificate tertanggal 02/4/2012 | 02 April 2012 | 20 December 2010 | 20 December 2010 | 02 April 2012 |
|
|
2010 | Pembangunan Hotel Lantai 5 Hotel Permata Krakatau PT. KIEC, ada unsur Instalasi Elektrikal Lainnya | 3408750 | PT. Krakatau Industrial Estate Cilegon | EL011 | 1 | HK.02.01/0034/2010 | Certificate Tertanggal 2/4/2012 | 02 April 2012 | 20 December 2010 | 20 December 2010 | 02 April 2012 |
|
|
2011 | Pekerjaan 200 MW Power Plant | 214545627 | PT. Posco E & C Indonesia | EL001 | 3 | Kontrak tanggal 7 Nopember 2011 | Final Acceptance Certification tanggal 09/10/2014 | 09 October 2014 | 07 November 2011 | 07 November 2011 | 09 October 2014 |
|
|
2014 | Pekerjaan Coal Fired Steam Turbine Power Plant Project 2x30 MW (Unit 1 & Unit 2) Amurang, Minahasa | 627190933 | PT. Megadaya Tangguh | EL001 | 1 | Kontrak tertanggal 17/4/2014 | Progress Report tanggal 14 September 2014 | 14 September 2014 | 14 April 2014 | 14 April 2014 | 14 September 2014 |
|
|
2009 | Pekerjaan Pembangunan Pusat Pergudangan Industri Perkayuan Berlokasi Di Komplek Pergudangan Avian | 83620597 | PT.MEBELINDO PRIMA PERKASA | BG003 | 1 | KONTRAK-066/MPP-KE/VIII/2009 | BASTP.I-071-/MPP-KE/III/2010 | 10 March 2010 | 11 August 2009 | 11 August 2009 | 10 March 2010 |
|
|
2007 | Pelaksanaan Pekerjaan Konstruksi Saluran Pipa Saluran Gas Anjungan Lepas Pantai dan Pemeliharaan Jaringan | 85924322 | PT CHEVRON PASIFIC INDONESIA | MK009 | 1 | KONTRAK-225/CPI-KE/VII/2007 | BAST.1-227/CPI-KE/II/2008 | 26 February 2008 | 23 July 2007 | 23 July 2007 | 26 February 2008 |
|
|
2010 | Pembangunan dan Perluasan Jembatan Sungai Cilik Riwut Palangka Raya | 17957500 | PT. BUANA NUSANTARA | SI004 | 1 | PERJ-001/BPN-KE/XII/2010 | 002/BAST-I/BPN-KE/VII/2011 | 11 July 2011 | 06 December 2010 | 06 December 2010 | 11 July 2011 |
|
|
2008 | Pembangunan Komplek Perkantoran dan Pertokoan Delta Sari Indah | 85775356 | PT INDOBATT INDUSTRI PERMAI | BG004 | 1 | PERJ-008/IIP-KE/Dir-X/2008 | 009/bast.01-IIP/KE-VI/2009 | 08 June 2009 | 29 October 2008 | 29 October 2008 | 08 June 2009 |
|
|
2010 | Pembangunan 40 Unit Rumah Type 36/135 dan Type 40/135 Perumahaan Pakuan Regency Di Bogor | 4684357 | PT.TRITUNGGAL PUTRA | BG001 | 1 | PERJ-114/TP-KE/X/2010 | BAST.01-117/TP-KE/V/2011 | 23 May 2011 | 21 October 2010 | 21 October 2010 | 23 May 2011 |
|
|
2012 | Instalasi Thermal dan Pemeliharaan Fasilitasi Produksi di Blok 4/2 Depot BBM Pertamina Mertasinga Cirebon | 83575745 | PT.FASHIONING OIL TECHNOLOGY | MK010 | 1 | PERJ-222/FOT-KE/VII/2012 | 238/BAST.1/FOT-KE/III/2013 | 13 March 2013 | 12 July 2012 | 12 July 2012 | 13 March 2013 |
|
|
2008 | Pembangunan Bedung dan Pintu III Bendung, Waduk Jatiluhur | 84134210 | PERUM JASA TIRTA II | SI001 | 1 | PERJ-551/PJT.II-KE/V/2008 | BAST.1-554/PJT.II/XII/2008 | 15 December 2008 | 07 May 2008 | 07 May 2008 | 15 December 2008 |
|
|
2009 | Pembangunan 315.000 Tpy Direct Rotary Kiln Kalimantan Ironmaking, ada unsur Instalasi Pembangkit Tenaga Listrik Daya Maks 10 MW | 64350240 | PT. Meratus Jaya Iron & Steel | EL002 | 1 | PROJ053/20/MJIS/II/2009 | Provisional Acceptance Certificate tgl 18/11/2012 | 18 November 2012 | 19 February 2009 | 19 February 2009 | 18 November 2012 |
|
|
2009 | Pembangunan 315.000 Tpy Direct Rotary Kiln Kalimantan Ironmaking, ada unsur Jaringan Distribusi Tenaga Listrik Tegangan Menengah | 94325517 | PT. Meratus Jaya Iron & Steel | EL006 | 1 | PROJ053/20/MJIS/II/2009 | Taking Over Certificate tgl 18/11/2012 | 18 November 2012 | 19 February 2009 | 19 February 2009 | 18 November 2012 |
|
|
2009 | Pekerjaan Pembangunan 315.000 TPY Reduction Rotary Kiln Plant Kalimantan Ironmaking Project , ada unsur Instalasi Tenaga Listrik Gedung dan Pabrik | 62883678 | PT. Meratus Jaya Iron & Steel | EL010 | 1 | PROJ053/20/MJIS/II/2009 | Provisional Acceptance Certificate tgl 27/5/2010 | 27 May 2010 | 19 February 2009 | 19 February 2009 | 27 May 2010 |
|
|
2009 | Pembangunan 315.000 Tpy Direct Rotary Kiln Kalimantan Iron Project PT. MJIS, ada unsur Instalasi Elektrikal Lainnya | 32175120 | PT. Meratus Jaya Iron & Steel | EL011 | 1 | PROJ053/20/MJIS/II/2009 | Provisional Acceptance Certificate tgl 18/11/2012 | 18 November 2012 | 19 February 2009 | 19 February 2009 | 18 November 2012 |
|
|
2009 | Pekerjaan 2X14 MW WHRB Power Plant for 315.000 TPY Direct Reduction Rotary Kiln Plant Kalimantan Ironmaking | 325614730 | PT. Meratus Jaya Iron & Steel | EL001 | 1 | PROJO53/20/MIJS/II/2009 | Certificate Provisional tanggal 18/11/2012 | 18 November 2012 | 19 February 2009 | 19 February 2009 | 18 November 2012 |
|
|
2010 | Proyek Power Plant PT MJIS | 268126000 | PT. Meratus Jaya Iron Steel | TI503 | 1 | PROJO53/20/MJIS/II/2009 | Cert. Date 7 Jan 2013 | 07 January 2013 | 19 February 2009 | 23 March 2010 | 07 January 2013 |
|
|
2011 | Pekerjaan Pengadaan Pipa Bawah Laut (Subsea Pipeline) & Pekerjaan Pemasangan Instalasi Pipa bawah Laut (Subsea Pipeline Installation) | 83698975 | PT. KARYA ADHI PERKASA | SI007 | 1 | SPB-00.48.11/DIV-II/KAPU/DIR-IV/2011-KE | BA.01-00.67.11/DIV-II/KAPU/DIR-I/2012-KE | 11 January 2011 | 11 April 2011 | 11 April 2011 | 11 January 2011 |
|
|
2007 | Pembangunan Unit Tanki Kilang Anjungan Lepas Pantai dan Instalasi Thermal serta Fasilitasi Blackloading MFO | 84120420 | PT PERTAMINA (Persero) | MK007 | 1 | SPB-02865/E18A00/2007-SO | 02871/BAST.I-E19A00/X/2008-SO | 24 March 2008 | 23 May 2007 | 23 May 2007 | 24 March 2008 |
|
|
2008 | Pekerjaan Pembangunan Pengolahaan Air Bersih/Pemasangan Pipa Intake,Pengendapan Filterisasi dan Reservendor Tanjung Palas | 17392605 | PT.PELTON INDONESIA | SI002 | 1 | SPK.111/PL-KE/IV/2008 | 114/PI-KE/BAST.1/IX/2008 | 22 September 2008 | 21 April 2008 | 21 April 2008 | 22 September 2008 |
|
|
2012 | Pembangunan Masjid Al Fattah Serta Renovasi Total Gedung Asrama Putra dan Putri AL-Idrisiyyah | 83820500 | PONDOK PESANTREN AL-IDRISIYYAH | BG009 | 1 | SPP-622/Pemb.YPPP.ALIdrisiyyah/X-2012 | BA.01-625/Pemb.Al-Idrisiyyah/VII/2013 | 29 July 2013 | 25 October 2012 | 25 October 2012 | 29 July 2013 |
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
| No | Nomor Kode | Kualifikasi | Asosiasi | Pengajuan Asosiasi | Persetujuan Pusat | Persetujuan LPJK | Cetak Registrasi Th Ke-2 |
|---|---|---|---|---|---|---|---|
| 1 | TI501 | B2 | GAPENRI | ||||
| 2 | TI503 | B2 | GAPENRI | ||||
| 3 | TI504 | B2 | GAPENRI | ||||
| 4 | EL001 | B2 | AKLI | 2016-08-31 | |||
| 5 | EL002 | B1 | AKLI | 2016-08-31 | |||
| 6 | EL004 | B2 | AKLI | 2016-08-31 | |||
| 7 | EL006 | B1 | AKLI | 2016-08-31 | |||
| 8 | EL007 | B1 | AKLI | 2016-08-31 | |||
| 9 | EL009 | B2 | AKLI | 2016-08-31 | |||
| 10 | EL010 | B1 | AKLI | 2016-08-31 | |||
| 11 | EL011 | B2 | AKLI | 2016-08-31 | |||
| 12 | SI005 | M1 | AKAINDO | ||||
| 13 | SI008 | B1 | AKAINDO | ||||
| 14 | BG001 | M2 | GAPENSI | ||||
| 15 | BG002 | M2 | GAPENSI | ||||
| 16 | BG003 | B2 | GAPENSI | ||||
| 17 | BG004 | B2 | GAPENSI | ||||
| 18 | BG006 | B2 | GAPENSI | ||||
| 19 | BG008 | B2 | GAPENSI | ||||
| 20 | BG009 | B2 | GAPENSI | ||||
| 21 | MK006 | B2 | GAPENSI | ||||
| 22 | MK007 | B2 | GAPENSI | ||||
| 23 | MK008 | M1 | GAPENSI | ||||
| 24 | MK009 | B2 | GAPENSI | ||||
| 25 | MK010 | B2 | GAPENSI | ||||
| 26 | SI001 | B2 | GAPENSI | ||||
| 27 | SI002 | B1 | GAPENSI | ||||
| 28 | SI003 | B2 | GAPENSI | ||||
| 29 | SI004 | B1 | GAPENSI | ||||
| 30 | SI007 | B2 | GAPENSI |
Catatan Proses (*) |
0. Permohonan Registrasi |
1. Proses Penilaian di Unit Sertifikasi |
2. Selesai Penilain di Unit Sertifikasi |
3. Proses Periode Registrasi |
4. Cetak Sertifikat |
5. Proses Pembayaran |
6. Selesai |
|
Nama Badan Usaha |
: |
KRAKATAU ENGINEERING |
Alamat Badan Usaha |
: |
Gedung Krakatau Steel Lt. 7, Jl. Jend. Gatot Subroto Kav. 54 |
Telepon |
: |
021-5221246 |
NPWP |
: |
01.067.815.9-051.000 |
| No | Nomor Kode | Kualifikasi | Asosiasi | Pengajuan Asosiasi | Persetujuan Pusat | Persetujuan LPJK | Cetak Registrasi Th Ke-3 |
|---|---|---|---|---|---|---|---|
| 1 | TI501 | B2 | GAPENRI | ||||
| 2 | TI503 | B2 | GAPENRI | ||||
| 3 | TI504 | B2 | GAPENRI | ||||
| 4 | EL001 | B2 | AKLI | ||||
| 5 | EL002 | B1 | AKLI | ||||
| 6 | EL004 | B2 | AKLI | ||||
| 7 | EL006 | B1 | AKLI | ||||
| 8 | EL007 | B1 | AKLI | ||||
| 9 | EL009 | B2 | AKLI | ||||
| 10 | EL010 | B1 | AKLI | ||||
| 11 | EL011 | B2 | AKLI | ||||
| 12 | SI005 | M1 | AKAINDO | ||||
| 13 | SI008 | B1 | AKAINDO | ||||
| 14 | BG001 | M2 | GAPENSI | ||||
| 15 | BG002 | M2 | GAPENSI | ||||
| 16 | BG003 | B2 | GAPENSI | ||||
| 17 | BG004 | B2 | GAPENSI | ||||
| 18 | BG006 | B2 | GAPENSI | ||||
| 19 | BG008 | B2 | GAPENSI | ||||
| 20 | BG009 | B2 | GAPENSI | ||||
| 21 | MK006 | B2 | GAPENSI | ||||
| 22 | MK007 | B2 | GAPENSI | ||||
| 23 | MK008 | M1 | GAPENSI | ||||
| 24 | MK009 | B2 | GAPENSI | ||||
| 25 | MK010 | B2 | GAPENSI | ||||
| 26 | SI001 | B2 | GAPENSI | ||||
| 27 | SI002 | B1 | GAPENSI | ||||
| 28 | SI003 | B2 | GAPENSI | ||||
| 29 | SI004 | B1 | GAPENSI | ||||
| 30 | SI007 | B2 | GAPENSI |
Catatan Proses (*) |
0. Permohonan Registrasi |
1. Proses Penilaian di Unit Sertifikasi |
2. Selesai Penilain di Unit Sertifikasi |
3. Proses Periode Registrasi |
4. Cetak Sertifikat |
5. Proses Pembayaran |
6. Selesai |
|