| Nama | : | IR. BABEL HAMBALI AKBAR |
| No. KTP | : | 3175040510660008 |
| Alamat | : | JL. BAING NO 20A RT:011 RW:004 KEL. TENGAH KEC. KRAMATJATI |
| NPWP | : | 57.105.490.7-005.000 |
Data Registrasi (sertifikat telah terbit):
Sub Klasifikasi |
Kualifikasi |
Asosiasi |
USTK |
LPJK Registrasi |
Tgl Registrasi |
Status Terakhir |
| AE401 - Ahli Teknik Tenaga Listrik | Utama | ATAKNAS | USTK LPJK Nasional | DKI Jakarta | 2020-08-19 | Sudah Terbit |
Data Riwayat Pendidikan :
Jenjang Pendidikan.. |
Nama Sekolah |
Jurusan |
Tahun Lulus |
No Ijasah |
| S1 | INSTITUT TEKNOLOGI NASIONAL | TEKNIK ELEKTRO | 1996 | A.2282.E.41/1995 |
Data Riwayat Kursus :
No Sertifikat |
Tahun |
Nama Kursus |
Data Riwayat Pekerjaan :
Nama Perusahaan |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
Data Riwayat Proyek :
Nama Proyek |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
| BMI | ME ENGINEER | 06-December-2018 S/D 12-December-2019 |
| MENARA ASTRA | ME ENGINEER | 04-December-2014 S/D 09-October-2018 |
| KAO NAPKIN | ME ENGINEER | 08-December-2013 S/D 27-August-2014 |
| KAO KKD | ME ENGINEER | 01-May-2012 S/D 05-October-2013 |
| NISSAN | ME ENGINEER | 16-June-2011 S/D 10-July-2012 |
| Pemasangan Sktm 20 Kv Kembangan Arah Gh.62/P | Project Manajer | 24-March-2011 S/D 21-September-2011 |
| NIPPRO | ME ENGINEER | 28-May-2010 S/D 20-April-2011 |
| Pembangunan Gardu Portal Rmu Lokasi Tipar Cakung | Project Manajer | 08-April-2010 S/D 06-October-2010 |
| Electrical Transmision & Distribution Pt Pln Cengkareng | Project Manajer | 19-April-2009 S/D 17-October-2009 |
| SEID | SITE ENGINEER | 05-December-2008 S/D 14-March-2010 |
| Pembangunan Gardu Traksi Di Cicayur (Paket 18) | Project Manajer | 26-April-2008 S/D 24-October-2008 |
| YKK PHASE II | SITE ENGINEER | 06-November-2007 S/D 02-October-2008 |
| Pembangunan Listrik Aliran Atas Jalur Ganda Antara Parungpanjang-Maja | Project Manajer | 22-March-2007 S/D 19-September-2007 |
| YKK PHASE I | SITE ENGINEER | 02-May-2006 S/D 11-September-2007 |
| Elektrifikasi Listrik Aliran Atas Track Exiting Antara Cisauk Cicayur | Project Manajer | 18-April-2006 S/D 16-October-2006 |
| Elektrifikasi Listrik Aliran Atas Track Eksisting Emplasemen Cilejit | Project Manajer | 10-January-2005 S/D 10-July-2005 |
| Pembangunan Gardu Portal Sisipan Di Jl. Patriot Kalimalang Area Pondok Kopi | Project Manajer | 10-February-2004 S/D 09-August-2004 |
| Peningkatan Gardu Listrik Eksisting Di Stasiun Kalideres Lintas Duri-Tangerang | Project Manajer | 21-May-2003 S/D 18-November-2003 |
| Pembangunan Gardu Induk Wilayah Jakarta Selatan Dan Revisi Gardu Induk Pln | Project Manajer | 11-January-2002 S/D 11-July-2002 |
| Pekerjaan Pemasangan Instalasi Listrik 1.000 Kva dan Pemasangan Instalasi Gardu Menteng Office Park | Project Manajer | 23-April-2001 S/D 21-October-2001 |