| Nama | : | IR LILIS ANDAYANI |
| No. KTP | : | 3276055606680002 |
| Alamat | : | BUMI AMPEL RAYA BLOK A 34 RT 002 RW 001 ABADIJAYA SUKAMAJAYA |
| NPWP | : | 48.428.804.8-412.000 |
Data Registrasi (sertifikat telah terbit):
Sub Klasifikasi |
Kualifikasi |
Asosiasi |
USTK |
LPJK Registrasi |
Tgl Registrasi |
Status Terakhir |
| AS201 - Ahli Teknik Bangunan Gedung | Madya | ATAKI | USTK LPJK DKI Jakarta | DKI Jakarta | 2020-07-28 | Sudah Terbit |
Data Riwayat Pendidikan :
Jenjang Pendidikan.. |
Nama Sekolah |
Jurusan |
Tahun Lulus |
No Ijasah |
| S1 | INSTITUT TEKNOLOGI SEPULUH NOPEMBER | TEKHIK SIPIL | 1991 | 08/ITSN/13/91 |
Data Riwayat Kursus :
No Sertifikat |
Tahun |
Nama Kursus |
Data Riwayat Pekerjaan :
Nama Perusahaan |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
Data Riwayat Proyek :
Nama Proyek |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
| [ACLAGE 4 RETEMDER 150 KV GIS EXTENSION FOR JAKARTA | PROJECT MANAGER | 27-March-2012 S/D 20-March-2018 |
| PACKAGE S-1 SUPPLY AND INSTALLATION 275 KV LAHAT LUBUK LINGGAU SUBSTATION | PROJECT MANAGER | 27-March-2012 S/D 20-March-2018 |
| 10000 MV PACKAGE 2.150 KV UGC AND GIS FOR WEST JAVA AND EAST JAVA | ENGINEER MANAGER | 08-June-2010 S/D 25-May-2017 |
| PEMBANGUNAN IBT KE 3 CILEGON BARU SERANG BANTEN | ENGINEER MANAGER | 21-October-2009 S/D 21-October-2011 |
| 1000 MW PACKAGE 1.50 KV UGC AND GIS FOR DKI | ENGINEER MANAGER | 05-June-2009 S/D 25-November-2012 |
| PACKAGE 3 : 150 KV CONVENTION SUBSTATION FOR JAWA | ENGINEERING MANAGER | 06-November-2008 S/D 01-August-2016 |
| PACKAGE 2:150 KV GAS INSULATED SWITCGEAR AND UNDER GROUND CABLE FOR WEST JAVA AND EAST JAVA | ENGINEERING MANAGER | 06-November-2008 S/D 25-June-2015 |
| PACKAGE 1:150 KV GAS INSULATED SWITCHGEAR AND UNDER GROUND CABLE FOR JAKARTA AND WEST JAVA | ENGINEERING MANAGER | 06-November-2008 S/D 13-February-2015 |
| PEMBANGUNAN DAN PERLUASAN GI 150 KV LEMBURSITU CIBADAK BARU CIAWI CIANJUR DAN BOGOR JKT / PLN | ENGINEER MANAGER | 24-September-2008 S/D 30-November-2012 |
| IFB 1 PROJECT 500 / 150 KV SUBSTATION | ENGINEER MANAGER | 05-March-2007 S/D 25-May-2009 |