| Nama | : | DARMAWAN |
| No. KTP | : | 6471050405700007 |
| Alamat | : | JL. RE MARTADINATA NO.02 037/- TELAGA SARI BALIKPAPAN SELATAN KALIMANTAN TIMUR |
| NPWP | : | 47.317.973.7-721.000 |
Data Registrasi (sertifikat telah terbit):
Sub Klasifikasi |
Kualifikasi |
Asosiasi |
USTK |
LPJK Registrasi |
Tgl Registrasi |
Status Terakhir |
| AL602 - Ahli Manajemen Proyek | Madya | PIPI | USTK LPJK DKI Jakarta | DKI Jakarta | 2019-06-12 | Sudah Terbit |
| AL603 - Ahli K3 Konstruksi | Madya | PIPI | USTK LPJK DKI Jakarta | DKI Jakarta | 2018-08-29 | Sudah Terbit |
Data Riwayat Pendidikan :
Jenjang Pendidikan.. |
Nama Sekolah |
Jurusan |
Tahun Lulus |
No Ijasah |
| S1 | INSTITUT SAINS DAN TEKNOLOGI NASIONAL | TEKNIK SIPIL | 1996 | F1SP/SP/106 NO:001620 |
Data Riwayat Kursus :
No Sertifikat |
Tahun |
Nama Kursus |
Data Riwayat Pekerjaan :
Nama Perusahaan |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
Data Riwayat Proyek :
Nama Proyek |
Jabatan |
Tgl Mulai S/D Tgl Akhir |
| Construction of Samurangau River Bridge | Project Manager | 04-February-2018 S/D 30-December-2018 |
| Proyek SNVT Perencanaan dan pengawasan Jalan dan Jembatan Kota Rantau ? Kandangan ? Mantimin ? Paringin ( Paket PW-12 ) | Project Manager | 29-April-2017 S/D 31-December-2017 |
| Paringin ( Paket PW-12 )Proyek SNVT Perencanaan dan pengawasan Jalan dan Jembatan Kota Rantau - Kandangan - Mantimin - | Project Manager | 09-April-2017 S/D 31-December-2017 |
| Proyek Teknik Pelebaran Jalan Ds. Tabur ( Bts. Kab Tabalong) ? Kelia dan Pasar Panas ? Kelua ( Paket PW -16 ) | Project Manager | 19-May-2015 S/D 31-December-2015 |
| Proyek Teknik Pelebaran Jalan Ds. Tabur ( Bts. Kab Tabalong) - Kelia dan Pasar Panas - Kelua ( Paket PW -16 ) | Project Manager | 19-May-2015 S/D 31-December-2015 |
| Proyek Pembangunan Gedung Stellbriz Building | KEPALA PROYEK | 03-May-2015 S/D 08-May-2016 |
| MOSQUE 1 BUILDING | KOORDINATOR PROYEK | 27-February-2014 S/D 27-July-2015 |
| TRAINING CENTER BULDING | KOORDINATOR PROYEK | 27-February-2014 S/D 27-July-2015 |
| WATER INJECTION FACILITY OF AMPUH PRESURE MAINTENANCE PROJECT | MANAJER PROYEK | 27-February-2014 S/D 27-October-2015 |
| Proyek Pembangunan Gedung Tarining Center Building PT. Karakatai Posco | KEPALA PROYEK | 14-February-2014 S/D 14-February-2015 |
| Mosque 1 Building | Project site Coordinator | 01-February-2014 S/D 01-April-2015 |
| Water Injection Facility of Ampuh Pressure Maintenance Project | Project Manager | 01-February-2014 S/D 01-April-2015 |
| Training Center Building | Project site Coordinator | 01-February-2014 S/D 01-April-2015 |
| MACHINERY SHOP EXT AND MOLD COATING | KOORDINATOR PROYEK | 27-December-2013 S/D 27-August-2014 |
| Construction Contract for Machinery Shop Construction Contract for Machinery Shop at Cilegon | Project site Coordinator | 01-December-2013 S/D 01-August-2014 |
| GATE & LANDSCAPE | KOORDINATOR PROYEK | 27-August-2013 S/D 27-December-2013 |
| Gate & Landscape | Project site Coordinator | 01-August-2013 S/D 01-December-2013 |
| PELEBARAN JALAN BATAS KOTA BALIKPAPAN SO 3 SAMBOJA KM 38 | MANAJER PROYEK | 27-May-2013 S/D 27-July-2013 |
| Proyek Pengawasan Pembangunan Jalan Paket 12 Ruas Sosok- Tanjung Provinsi Kalimantan Barat | Project Manager | 01-May-2013 S/D 31-December-2013 |
| Proyek Pengawasan Pembangunan Jalan Paket 12 Ruas Sosok- Tanjung Provinsi Kalimantan Barat | Project Manager | 01-May-2013 S/D 31-December-2013 |
| Pelebaran Jalan Batas Kota Balikpapan SP.3 - Samboja Km.38 Balikpapan | Project Manager | 01-February-2013 S/D 01-October-2013 |
| DORMITORY BUILDING | KOORDINATOR PROYEK | 27-May-2012 S/D 27-April-2013 |
| Dormitory Building | Project site Coordinator | 01-May-2012 S/D 01-April-2013 |
| Proyek Pembangunan Dormitory Building PT. Krakatau Posaco | KEPALA PROYEK | 01-May-2012 S/D 01-May-2013 |
| Proyek Pengawan Teknis Pemeliharaan Berkala Jalan Sp. Serapai ? Marabahan & Pemeliharaan Berkala Jalan Pangeran Samudera ( Banjarmasin ) | Project Manager | 01-April-2012 S/D 30-November-2012 |
| Proyek Pengawan Teknis Pemeliharaan Berkala Jalan Sp. Serapai - Marabahan & Pemeliharaan Berkala Jalan Pangeran Samudera ( Banjarmasin ) | Project Manager | 01-April-2012 S/D 30-November-2012 |
| HEADQUARTER AND RESTAURANT BUILDING | KOORDINATOR PROYEK | 27-January-2012 S/D 27-April-2013 |
| Headquarter and Restaurant Building | Project site Coordinator | 01-January-2012 S/D 01-April-2013 |
| PENANGANAN LONGSORAN AREAL SQUASH | MANAJER PROYEK | 27-November-2011 S/D 27-March-2012 |
| Penangan Longsoran Areal Squash | Project Manager | 01-November-2011 S/D 01-March-2012 |
| PENYEMPURNAAN AREAL GEDUNG SQUASH | MANAJER PROYEK | 27-September-2011 S/D 27-February-2012 |
| Penyempurnaan Areal Gedung Squash | Project Manager | 01-September-2011 S/D 01-February-2012 |
| Proyek Peningkatan Jalan Balikpapan - Gereja ( KM.55 ) | Project Manager | 01-June-2011 S/D 31-October-2011 |
| Proyek Peningkatan Jalan Balikpapan ? Gereja ( KM.55 ) | Project Manager | 01-June-2011 S/D 31-October-2011 |
| Proyek Pembangunan Gedung Squash Balikpapan | KEPALA PROYEK | 01-February-2011 S/D 01-February-2012 |
| ENGINEERING DESIGN FOR LANDSLIDE CHVRON PASIR RIDGE | MANAJER PROYEK | 27-July-2010 S/D 27-July-2011 |
| PENYELESAIAN PEMBANGUNAN GEDUNG SQUASH ( INFRA STRUKTUR ) | MANAJER PROYEK | 27-February-2010 S/D 27-August-2011 |
| Penyelesaian Pembangunan Gedung Squash (Infra Struktur) | Project Manager | 01-February-2010 S/D 01-August-2011 |
| Proyek Pembangunan Gedung Reagional Treasury Marketing ( RTM ) Medan | KEPALA PROYEK | 01-September-2009 S/D 01-September-2010 |
| CONSTRUCTION LANDSLIDE CHEVRON PASIR RIDGE BALIKPAPAN | MANAJER PROYEK | 27-July-2009 S/D 27-July-2010 |
| Proyek Rehabilitasi / Pemeliharaan Jalan KM. 38 Semoi Sepaku | Project Manager | 01-April-2009 S/D 30-November-2009 |
| CONTAIMINATED SOIL REPLACEMENT CHEVRON TANJUNG JUMLAI | MANAJER PROYEK | 27-July-2008 S/D 27-July-2009 |
| ENGINEERING DESIGN SEPINGGAN DAN YAKIN FIELD | TEAM LEADER | 27-June-2008 S/D 27-September-2009 |
| Engineering Design Sepinggan dan Yakin Field | Team Leader | 01-June-2008 S/D 01-September-2009 |
| Proyek Pembangunan Gedung AXA Mandiri Financial Servies ( AMFS ) Semarang | KEPALA PROYEK | 09-April-2008 S/D 09-April-2009 |
| Proyek Pembangunan Jalan Akses A Rifaddin - Stadio Utama - Samarinda | Project Manager | 01-March-2008 S/D 30-December-2008 |
| PEMBANGUNAN LAPANGAN SQUASH ( VENUES PON 2008 ) | CONSTRUCTION MANAGER | 27-November-2007 S/D 27-April-2008 |
| GHSF ROW ROAD LANDSLIDE SAPI TO TOTAL TIE IN CHEVRON HANDIL | MANAJER PROYEK | 27-June-2007 S/D 27-April-2008 |
| GHSF Row Road and Landslide SAPI to TOTAL Tie In - Chevron Handil | Project Manager | 01-June-2007 S/D 01-April-2008 |
| MOB ROOF REPAIR CHEVRON PASIR RIDGE | MANAJER PROYEK | 27-April-2007 S/D 27-September-2008 |
| Proye Pembangunan Gedung Bank Internasional Indonesia ( BII ) Batam Center | KEPALA PROYEK | 01-February-2007 S/D 01-February-2008 |
| Engineering Design for Landslide - Chevron Pasir Ridge | Project Manager | 01-February-2007 S/D 01-April-2008 |
| Construction Landslide-Chevron Pasir Ridge Balikpapan | Project Manager | 01-February-2007 S/D 01-April-2008 |
| Contaiminated Soil Replacement - Chevron Tanjung Jumlai | Project Manager | 01-February-2007 S/D 01-April-2008 |
| Proyek Pembangunan Jalan A Yani Cs - P. Suryanata Cs Samarinda | Project Manager | 01-June-2006 S/D 30-March-2007 |
| Pembangunan GOR dan Graha Pemuda Kota Balikpapan, Kalimantan Timur | Project Manager | 01-February-2006 S/D 01-April-2007 |
| Proyek Pembangunan Gedung Pabrik KBN A.15 - 16 Kawasan Berikat Nusantara | KEPALA PROYEK | 05-January-2006 S/D 05-November-2006 |
| Proyek Perencanaan dan Pengawasan Jalan dan Jembatan Provinsi Sulawesi Tenggara/Core Team 9 Paket - 15 ) | Project Manager | 01-April-2005 S/D 30-November-2005 |
| HANDIL CIVIL FACILITIES GTS TUNU PHASE 10 | MANAJER PROYEK | 27-March-2005 S/D 27-January-2007 |
| Handil Civil Facilities GTS Tunu Phase 10 | Project Manager | 01-February-2005 S/D 01-April-2006 |
| Proyek Pembangunan Gedung Arcadia Office Park Blok B & C Jakarta | KEPALA PROYEK | 01-September-2004 S/D 01-September-2005 |
| ROAD MAINTENANCE ON JL SOEKARNO HATTA ( KM -0 UNTIL KM -55 ) | MANAJER PROYEK | 27-April-2004 S/D 27-November-2004 |
| Road Maintenance on Jl. Soekarno Hatta (KM-0 until KM-55) | Project Manager | 01-February-2004 S/D 01-April-2005 |
| SOMBER BRIDGE EXPANSION AND REPAIR | MANAJER PROYEK | 27-November-2003 S/D 27-December-2003 |
| Proyek Peningkatan Jalan Kabupaten Penajam Pasaer Utara Wilayah Babulu | Project Manager | 18-September-2003 S/D 11-March-2004 |
| Proyek Pembangunan Gedung Rumah Sakit Al - Islam | KEPALA PROYEK | 01-April-2003 S/D 01-April-2004 |
| Road Maintenance including Rigit Pavement Construction on Jl. Soekarno Hatta | Project Manager | 01-February-2003 S/D 01-December-2003 |
| Concrete Retaining Wall for Landslide Repair on Jl. Syarifudin Yoes | Project Manager | 01-February-2003 S/D 01-December-2003 |
| CONCRETE RETAINING WALL FOR LANSLIDE REPAIR ON JL SOEKARNO HATTA KM 4.5 | MANAJER PROYEK | 27-July-2002 S/D 27-November-2002 |
| CONCRETE RETAINING WALL FOR LANDSLIDE REPAIR ON JL SYARIFUDIN YOES | MANAJER PROYEK | 27-May-2002 S/D 27-December-2002 |
| ROAD MAINTENANCE INCLUDING RIGIT PAVEMENT CONSTRUCTION ON JL SOEKARNO HATTA | MANAJER PROYEK | 27-April-2002 S/D 27-November-2002 |
| Somber Bridge Expansion and Repair | Project Manager | 01-February-2002 S/D 01-April-2003 |
| Concrete Retaining Wall for Landslide Repair on Jl. Soekarno Hatta Km. 4.5 | Project Manager | 01-February-2002 S/D 01-April-2003 |
| CONCRETE RETAINING WALL FOR LANDSLIDE REPAIR III ON JL ISWAHYUDI | MANAJER PROYEK | 27-November-2001 S/D 27-October-2001 |
| CONCRETE RETAINING WALL FOR LANDSLIDE REPAIR ON JL SOEKARNO HATTA KM 2.5 | MANAJER PROYEK | 27-May-2001 S/D 27-October-2001 |
| Concrete Retaining Wall for Landslide Repair on Jl. Soekarno Hatta Km. 2.5 | Project Manager | 01-February-2001 S/D 01-April-2002 |
| Concrete Retaining Wall for Landslide Repair III on Jl. Iswahyudi | Project Manager | 01-February-2001 S/D 01-April-2002 |
| CONCERETE SHEET PILE BETWEEN JL MT HARYONO AND JL ISWAHYUDI PHASE III | MANAJER PROYEK | 27-November-2000 S/D 27-December-2001 |
| CONCRETE RETAINING WALL FOR LANSLIDE REPAIR II ON JL ISWAHYUDI | MANAJER PROYEK | 27-July-2000 S/D 27-October-2001 |
| VARIOUS CIVIL WORKS AT SEPINGGAN | MANAJER PROYEK | 27-May-2000 S/D 27-May-2001 |
| Concrete Retaining Wall for Landslide Repair II on Jl. Iswahyudi | Project Manager | 01-February-2000 S/D 01-April-2001 |
| Concrete Sheet Pile Between Jl. MT Haryono and Jl. Iswahyudi - Phase III | Project Manager | 01-February-2000 S/D 01-April-2001 |
| Various Civil Works at Sepinggan | Project Manager | 01-February-2000 S/D 01-April-2001 |
| Proyek Pembangunan Gedung Badan Koordinasi Penannaman Modal ( BKPM ) | KEPALA PROYEK | 01-May-1999 S/D 01-May-2001 |
| Peciko Field Development Project | Engineering Coordinator | 01-February-1998 S/D 01-April-2000 |
| Traders Hotel Project - 17 Flr | Site Construction Engineer | 01-February-1997 S/D 01-April-1998 |
| Institute Sains and Technology National (ISTN) | Workshop Instructor | 01-February-1991 S/D 01-April-1996 |